IEEE 62271-37-013-2015
$105.63
IEEE/IEC International Standard for High-voltage switchgear and controlgear — Part 37-013: Alternating-current generator circuit-breakers
Published By | Publication Date | Number of Pages |
IEEE | 2015 | 226 |
Revision Standard – Active.
PDF Catalog
PDF Pages | PDF Title |
---|---|
1 | IEC/IEEE 62271-37-013 Front Cover |
3 | Title page |
4 | CONTENTS |
14 | FOREWORD |
16 | 1 General 1.1 Scope 1.2 Normative references |
17 | 2 Normal and special service conditions 2.1 Normal service conditions 2.2 Special service conditions 3 Terms and definitions |
18 | 3.1 General terms |
20 | 3.2 Assemblies of switchgear and controlgear 3.3 Parts of assemblies 3.4 Switching devices |
22 | 3.5 Parts of generator circuit-breakers |
25 | 3.6 Operation |
27 | 3.7 Characteristic quantities |
37 | Figures Figure 1 – Typical oscillogram of a three-phase short-circuit make-break cycle |
38 | Figure 2 – Generator circuit-breaker without resistors – Opening operation Figure 3 – Generator circuit-breaker without resistors – Close-open cycle |
39 | Figure 4 – Generator circuit-breaker with opening resistors – Opening operation Figure 5 – Generator circuit-breaker with opening resistors – Close-open cycle |
40 | Figure 6 – Example of a three-phase asymmetrical current |
41 | Figure 7 – Examples of possible valid interruptions in a phase with intermediate level of asymmetry after a major loop and a corresponding time t1 |
42 | 3.8 Index of definitions Figure 8 – Examples of possible valid interruptions in a phase with intermediate level of asymmetry after a minor loop and a corresponding time t2 |
46 | 4 Ratings 4.1 Rated voltage Ur 4.2 Rated insulation level |
47 | 4.2.101 Dielectric strength 4.2.102 Rated power frequency withstand voltage Ud 4.2.103 Rated lightning impulse withstand voltage Up 4.3 Rated frequency fr 4.4 Rated normal current Ir and temperature rise 4.4.1 Rated normal current Ir Tables Table 1 – Rated insulation levels for a.c. generator circuit-breakers |
48 | 4.4.2 Temperature rise 4.4.3 Particular points of Table 3 of IEC 62271-1:2007 4.4.101 Emergency current ratings during loss of cooling |
49 | 4.5 Rated short-time withstand current Ik 4.6 Rated peak withstand current Ip 4.7 Rated duration of short circuit tk Figure 9 – Effect of various cooling failures and subsequent load reductions on generator circuit-breaker temperature |
50 | 4.8 Rated supply voltage of closing and opening devices and of auxiliaryand control circuits Ua 4.8.1 General 4.8.2 Rated supply voltage Ua 4.8.3 Tolerances |
51 | 4.8.4 Ripple voltage 4.8.5 Voltage drop and supply interruption 4.9 Rated supply frequency of closing and opening devices and auxiliary circuits 4.10 Rated pressure of compressed gas supply for controlled pressure systems 4.11 Rated filling levels for insulation, interruption and/or operation Table 2 – Preferred values of supply voltages and theirranges for closing and opening devices and of auxiliaryand control circuits of generator circuit-breakers |
52 | 4.101 Rated short-circuit current 4.101.1 General 4.101.2 Rated system-source short-circuit breaking current |
53 | Figure 10 – Typical asymmetrical system-source short-circuit current |
54 | 4.101.3 Rated generator-source short-circuit breaking current Figure 11 – Degree of asymmetry as a function of time after fault initiation |
55 | Figure 12 – Typical asymmetrical generator-source short-circuit current with a strong decrement of the a.c. component |
56 | 4.101.4 Rated single-phase-to-earth fault breaking current 4.102 Rated peak short-circuit making current IMC 4.103 Rated load making and breaking current |
57 | 4.104 Rated out-of-phase making and breaking current 4.105 Rated transient recovery voltage (TRV) related to the breaking currents 4.105.1 Representation of TRV waves |
58 | 4.105.2 Rated values of TRV Figure 13 – 2-parameter representation of prospective TRV waveform for interrupting three-phase symmetrical faults Table 3 – TRV parameters for system-source faults |
59 | 4.106 Standard operating sequence 4.106.1 General Table 4 – TRV parameters for generator-source faults Table 5 – TRV parameters for load current switching Table 6 – TRV parameters for out-of-phase current switching |
60 | 4.106.2 Rated short-circuit current operating sequence 4.106.3 Rated load current operating sequence 4.106.4 Rated out-of-phase current operating sequence 4.107 Rated time quantities 4.107.1 General 4.107.2 Rated break-time |
61 | 4.107.3 Rated minimum opening time 4.108 Mechanical operation endurance capability classes M1 and M2 5 Design and construction 5.1 Requirements for liquids in generator circuit-breakers |
62 | 5.2 Requirements for gases in generator circuit-breakers 5.3 Earthing of generator circuit-breakers 5.4 Auxiliary and control equipment |
63 | 5.5 Dependent power operation 5.6 Stored energy operation 5.7 Independent manual or power operation (independent unlatched operation) 5.8 Operation of releases 5.8.1 Shunt closing release 5.8.2 Shunt opening release 5.8.3 Capacitor operation of shunt releases 5.8.4 Under-voltage release 5.8.101 Multiple releases 5.8.102 Operation limits of releases 5.8.103 Power consumption of releases |
64 | 5.9 Low- and high-pressure interlocking devices 5.10 Nameplates Table 7 – Nameplate information |
66 | 5.10.101 Accessories 5.10.102 Modification of generator circuit-breakers 5.11 Interlocking devices 5.12 Position indication 5.13 Degrees of protection provided by enclosures |
67 | 5.13.1 Protection of persons against access to hazardous parts and protection of the equipment against ingress of solid foreign objects (IP coding) 5.13.2 Protection against ingress of water (IP coding) 5.13.3 Protection of equipment against mechanical impact under normal service conditions (IK coding) 5.14 Creepage distances for outdoor insulators 5.15 Gas and vacuum tightness 5.16 Liquid tightness 5.17 Fire hazard (flammability) 5.18 Electromagnetic compatibility (EMC) 5.19 X-ray emission 5.20 Corrosion 5.101 Requirements for simultaneity of poles during single closing and single opening operations |
68 | 5.102 General requirement for operation 5.103 Pressure limits of fluids for operation 5.104 Vent outlets 5.105 Warning labels 5.106 Instructions |
69 | 6 Type tests |
70 | 6.1 General 6.1.1 Grouping of tests 6.1.2 Information for identification of specimens 6.1.3 Information to be included in type-test reports 6.2 Dielectric tests 6.2.1 Ambient air conditions during tests Table 8 – Type tests |
71 | 6.2.2 Wet test procedure 6.2.3 Condition of the generator circuit-breaker during dielectric tests 6.2.4 Criteria to pass the test 6.2.5 Application of test voltage and test conditions 6.2.6 Tests of generator circuit-breakers of Ur ≤ 245 kV |
72 | 6.2.7 Tests of generator circuit-breakers of Ur < 245 kV 6.2.8 Artificial pollution tests for outdoor insulators 6.2.9 Partial discharge tests 6.2.10 Dielectric tests on auxiliary and control circuits 6.2.11 Voltage test as a condition check 6.3 Radio interference voltage (r.i.v.) tests |
73 | 6.4 Measurement of the resistance of circuits 6.4.1 Main circuit 6.4.2 Auxiliary circuits 6.5 Temperature-rise tests 6.5.1 Conditions of the generator circuit-breaker to be tested 6.5.2 Arrangement of the equipment |
74 | Table 9 – Conditions during temperature rise test |
75 | 6.5.3 Measurement of the temperature and the temperature rise 6.5.4 Ambient air temperature 6.5.5 Temperature-rise tests of the auxiliary and control equipment Figure 14 – Typical temperature rise test setup forsingle-phase-enclosed generator circuit-breakers (top view) |
76 | 6.5.6 Interpretation of the temperature-rise tests 6.5.101 Demonstrations of emergency conditions 6.6 Short-time withstand current and peak withstand current tests 6.6.1 Arrangement of the generator circuit-breaker and of the test circuit 6.6.2 Test current and duration 6.6.3 Behaviour of generator circuit-breaker during test 6.6.4 Conditions of generator circuit-breaker after test |
77 | 6.7 Verification of the degree of protection 6.7.1 Verification of the IP coding 6.7.2 Verification of the IK coding 6.8 Tightness tests 6.9 Electromagnetic compatibility (EMC) tests 6.10 Additional tests on auxiliary and control circuits 6.10.1 General 6.10.2 Functional tests 6.10.3 Electrical continuity of earthed metallic parts test 6.10.4 Verification of the operational characteristics of auxiliary contacts 6.10.5 Environmental tests |
78 | 6.10.6 Dielectric tests 6.11 X-radiation test procedure for vacuum interrupters 6.101 Mechanical and environmental tests 6.101.1 Miscellaneous provisions for mechanical and environmental tests |
81 | 6.101.2 Mechanical operation test at ambient air temperature |
82 | Table 10 – Number of operating sequences Table 11 – Operations to be performed before and after the test programme |
83 | 6.101.3 Low and high temperature tests |
87 | 6.101.4 Sound level tests 6.102 Miscellaneous provisions for making and breaking tests 6.102.1 General Figure 15 – Test sequences for low and high temperature tests |
88 | 6.102.2 Number of test specimens 6.102.3 Arrangement of generator circuit-breaker for tests |
90 | 6.102.4 General considerations concerning testing methods |
91 | Figure 16 – Reference mechanical travel characteristics (idealised curve) |
92 | Figure 17 – Reference mechanical travel characteristics (idealised curve) with the prescribed envelopes centered over the reference curve (+5 %, –5 %), contact separation in this example at time t = 20 ms Figure 18 – Reference mechanical travel characteristics (idealised curve) with the prescribed envelopes fully displaced upward from the reference curve (+10 %, –0 %), contact separation in this example at time t = 20 ms |
93 | Figure 19 – Reference mechanical travel characteristics (idealised curve) with the prescribed envelopes fully displaced downward from the reference curve (+0 %, –10 %), contact separation in this example at time t = 20 ms |
94 | Figure 20 – Equivalent testing set-up for unit testing of generator circuit-breakers with more than one separate interrupter units |
96 | 6.102.5 Synthetic tests 6.102.6 No-load operations before tests 6.102.7 Alternative operating mechanisms |
97 | 6.102.8 Behaviour of generator circuit-breaker during tests |
98 | 6.102.9 Condition of generator circuit-breaker after tests |
100 | 6.102.10 Demonstration of the most severe switching conditions |
102 | Figure 21 – Two valid three-phase symmetrical breaking operations |
104 | Figure 22 – Three-phase asymmetrical breaking operation – Minimum arcing time with intermediate asymmetry after major loop (tarc min 1) |
105 | Figure 23 – Three-phase asymmetrical breaking operation – Maximum arcing time for the first-pole-to-clear after major loop (tarc max 1) |
106 | Figure 24 – Three-phase asymmetrical breaking operation – Minimum arcing time with intermediate asymmetry after minor loop (tarc min 2) |
107 | Figure 25 – Three-phase asymmetrical breaking operation – Maximum arcing time for the last-pole-to-clear after extended major loop (tarc max 2) |
109 | Figure 26 – Single-phase asymmetrical breaking operation – Minimum arcing time with intermediate asymmetry after major loop (tarc min 1) |
110 | Figure 27 – Single-phase asymmetrical breaking operation – Maximum arcing time for the first-pole-to-clear after major loop (tarc max 1) |
111 | Figure 28 – Single-phase asymmetrical breaking operation – Minimum arcing time with intermediate asymmetry after a minor loop (tarc min 2) |
112 | Figure 29 – Single-phase asymmetrical breaking operation – Maximum arcing time for the last-pole-to-clear extended major loop (tarc max 2) |
113 | Table 12 – Test parameters for 50 Hz asymmetrical system-source fault test-duties for the first-pole-to-clear |
114 | Table 13 – Test parameters for 60 Hz asymmetrical system-source fault test-duties for the first-pole-to-clear |
115 | Table 14 – Test parameters for 50 Hz asymmetrical system-source fault test-duties for the last-pole-to-clear |
116 | Table 15 – Test parameters for 60 Hz asymmetrical system-source fault test-duties for the last-pole-to-clear |
117 | 6.102.11 Methods of determining prospective transient recovery voltage waves 6.103 System-source short-circuit making and breaking tests 6.103.1 Power factor of test circuit 6.103.2 Frequency of test circuit 6.103.3 Earthing of test circuit |
118 | Figure 30 – Earthing of test circuits for three-phase short-circuit tests, first-pole-to-clear factor 1,5 Figure 31 – Earthing of test circuits for single-phase short-circuit tests, first-pole-to-clear factor 1,5 |
119 | 6.103.4 Connection of test circuit to generator circuit-breaker 6.103.5 Applied voltage for system-source short-circuit making tests 6.103.6 System-source short-circuit making current 6.103.7 System-source short-circuit breaking current |
120 | 6.103.8 Transient recovery voltage (TRV) for system-source short-circuit breaking tests |
121 | 6.103.9 Measurement of transient recovery voltage during test 6.103.10 Power frequency recovery voltage 6.103.11 System-source short-circuit test operating sequence 6.103.12 System-source short-circuit test-duties |
122 | Table 16 – Test duties to demonstrate the system-source short-circuit makingand breaking current capability for three-phase tests |
123 | 6.104 Load current breaking tests 6.104.1 General Table 17 – Test duties to demonstrate the system-source short-circuit makingand breaking current capability for single-phase tests |
124 | 6.104.2 Conditions of test severity 6.104.3 Number of tests 6.105 Generator-source short-circuit current making and breaking tests 6.105.1 Power factor of test circuit 6.105.2 Frequency of test circuit |
125 | 6.105.3 Earthing of test circuit 6.105.4 Connection of the test circuit to the generator circuit-breaker 6.105.5 Applied voltage for generator-source short-circuit making tests |
126 | 6.105.6 Generator-source short-circuit making current 6.105.7 Generator-source short-circuit breaking current |
127 | 6.105.8 Transient recovery voltage (TRV) for generator-source short-circuit breaking tests 6.105.9 Measurement of transient recovery voltage during test 6.105.10 Power frequency recovery voltage 6.105.11 Generator-source short-circuit test operating sequence 6.105.12 Generator-source short-circuit breaking test-duties |
128 | Figure 32 – Example of a valid prospective test current for test-duty 5 Figure 33 – Example of a valid test for test-duty 5 |
129 | Figure 34 – Example of an invalid test for test-duty 5 Figure 35 – Second example of a valid test for test-duty 5 |
130 | Figure 36 – Example of a valid prospective test current for test-duties 6A and 6B Figure 37 – Example of a valid test for test-duties 6A and 6B |
131 | Figure 38 – Example of a valid test for test-duties 6A and 6B |
132 | Table 18 – Test duties to demonstrate the generator-source short-circuit making and breaking current capability for three-phase tests |
133 | 6.106 Out-of-phase making and breaking tests 6.106.1 General Table 19 – Test duties to demonstrate the generator-source short-circuit making and breaking current capability for single-phase tests |
134 | 6.106.2 Out-of-phase current switching capability 6.106.3 Conditions of test severity |
135 | Table 20 – Test duties to demonstrate the out-of-phase currentswitching capability for three-phase tests |
136 | 6.106.4 Test circuit Table 21 – Test duties to demonstrate the out-of-phase current switching capability for single-phase tests |
137 | Figure 39 – Test circuit for single-phase out-of-phase tests Figure 40 – Test circuit for out-of-phase tests using two voltagesseparated by 120 electrical degrees Figure 41 – Test circuit for out-of-phase tests with one terminal of the generatorcircuit-breaker earthed (subject to agreement of the manufacturer) |
138 | 6.106.5 Applied voltage before out-of-phase making tests 6.106.6 Transient recovery voltage (TRV) for out-of-phase breaking tests 6.106.7 Demonstration of the most severe switching conditions during test-duty OP1 6.106.8 Demonstration of the most severe switching conditions during test-duty OP2 7 Routine tests |
139 | 7.1 Dielectric test on the main circuit 7.2 Tests on auxiliary and control circuits 7.2.1 Inspection of auxiliary and control circuits, and verification of conformity to the circuit diagrams and wiring diagrams 7.2.2 Functional tests 7.2.3 Verification of protection against electrical shock 7.2.4 Dielectric tests |
140 | 7.3 Measurement of the resistance of the main circuit 7.4 Tightness test 7.4.1 Controlled pressure systems for gas 7.4.2 Closed pressure systems for gas 7.4.3 Sealed pressure systems 7.4.4 Liquid tightness tests |
141 | 7.5 Design and visual checks 7.101 Mechanical operating tests |
142 | 8 Guide to the selection of generator circuit-breakers 8.101 General |
143 | 8.102 General application conditions 8.102.1 Normal service conditions 8.102.2 Special service conditions |
145 | 8.103 Application consideration 8.103.1 General 8.103.2 Rated voltage 8.103.3 Rated insulation level |
146 | 8.103.4 Rated frequency 8.103.5 Rated normal current 8.103.6 Short-circuit current rating |
147 | Figure 42 – General circuit diagram of a power station |
149 | Figure 43 – Generator-source short-circuit current |
150 | Figure 44 – Generator-source short-circuit current in case of generator delivering power with lagging or leading power factor prior to fault initiation |
151 | Figure 45 – Short-circuit current for generator-source fault |
152 | Figure 46 – Short-circuit current with circuit-breaker arc voltageafter contact separation |
161 | 8.103.7 TRV rating for system-source and generator-source short-circuits Figure 47 – Single-line diagram of a power station with two generators connected to the high-voltage system by means of a three-winding step-up transformer |
163 | Figure 48 – Single-line diagram of unit generator system Figure 49 – Single-line diagram of half-sized transformer unit system |
164 | Figure 50 – Single-line diagram of system with half-sized generators |
167 | 8.103.8 Rated load making and breaking current |
168 | Figure 51 – Single-line diagram of power system Figure 52 – Equivalent circuit of power system |
169 | Figure 53 – Voltage diagram for lagging power factor load Figure 54 – Voltage diagram for unity power factor load Figure 55 – Recovery voltage across the generator circuit-breaker |
170 | Figure 56 – TRV curve for the first-pole-to-clear |
171 | 8.103.9 Rated out-of-phase making and breaking current |
172 | 8.103.10 Excitation switching current |
173 | 8.103.11 Capacitive switching current 9 Information to be given with enquiries, tenders and orders |
175 | 10 Rules for transport, storage, installation, operation and maintenance 10.1 Conditions during transport, storage and installation |
176 | 10.2 Installation 10.2.1 Unpacking and lifting 10.2.2 Assembly 10.2.3 Mounting 10.2.4 Connections 10.2.5 Final installation inspection |
177 | 10.2.6 Basic input data by the user 10.2.7 Basic input data by the manufacturer 10.2.101 Commissioning tests |
178 | 10.2.102 Commissioning checks and test programme |
181 | 10.3 Operation |
182 | 10.4 Maintenance 10.4.1 General 10.4.2 Recommendations for the manufacturer |
183 | 10.4.3 Recommendations for the user 10.4.4 Failure report |
185 | 11 Safety 11.1 Precautions by manufacturers 11.2 Precautions by users |
186 | 11.3 Electrical aspects 11.4 Mechanical aspects |
187 | 11.5 Thermal aspects 11.6 Operation aspects 12 Influence of the product on the environment |
188 | Annex A (normative)Tolerances on test quantities during type tests |
189 | Table A.1 – Tolerances on test quantities for type tests |
192 | Annex B (normative)Records and reports of type tests according to6.6, 6.103, 6.104, 6.105 and 6.106 B.1 Information and results to be recorded B.2 Information to be included in type test reports B.2.1 General B.2.2 Apparatus tested B.2.3 Rated characteristics of generator circuit-breaker, including its operating devices and auxiliary equipment |
193 | B.2.4 Test conditions (for each series of tests) B.2.5 Short-circuit making and breaking tests |
194 | B.2.6 Short-time withstand current test B.2.7 No-load operation B.2.8 Out-of-phase making and breaking tests |
195 | B.2.9 Load current switching tests B.2.10 Oscillographic and other records |
196 | Annex C (…) |
197 | Annex D (normative)Use of mechanical characteristics and related requirements |
198 | Annex E (informative)Example of the application of a generator circuit-breaker E.1 General E.2 System characteristics Figure E.1 – Single-line station diagram |
199 | Table E.1 – System characteristics |
200 | E.3 System-source short-circuit current E.3.1 AC component of the system-source short-circuit breaking current |
201 | E.3.2 System-source asymmetrical short-circuit breaking current |
203 | E.4 Generator-source short-circuit current E.4.1 AC component of the generator-source short-circuit breaking current |
204 | E.4.2 Generator-source asymmetrical short-circuit breaking current |
205 | Figure E.2 – Asymmetrical generator-source short-circuit currentwith no arc at the fault location |
206 | E.5 Transient recovery voltage E.6 Out-of-phase conditions Figure E.3 – Asymmetrical generator-source short-circuit currentwith arc at the fault location |
207 | Figure E.4 – Schematic diagram of power station(single-line diagram as in Figure 48) |
209 | E.7 Normal current application Figure E.5 – Prospective fault current considering the moment of inertia of the synchronous machine and resulting from synchronizing under out-of-phase conditions (out-of-phase angle φ0 = 90°, fault initiation at UA = 0) |
210 | E.8 Generator circuit-breaker electrical characteristics Figure E.6 – Generator circuit-breaker temperature and load current with loss of coolant |
212 | Annex F (informative)For generator circuit-breakers connected to the step-up transformer by shielded cables – An example of the effects of added capacitance on TRV requirements for a system-source fault |
213 | Figure F.1 – TRV rate-of-rise for system-source faults: transformersrated from 65,5 MVA to 100 MVA Figure F.2 – TRV peak (uc) multipliers for system-source faults:transformers rated from 65,5 MVA to 100 MVA |
214 | Figure F.3 – TRV rate-of-rise for system-source faults: transformers rated from 10 MVA to 50 MVA Figure F.4 – TRV peak (uc) multipliers for system-source faults:transformers rated from 10 MVA to 50 MVA |
215 | Annex G (informative)Symbols and related terminology G.1 Comparison of IEEE and IEC electrical terms and symbols Table G.1 – Comparison of IEEE and IEC electrical terms and symbols |
216 | G.2 Comparison between TRV terminology and symbols |
217 | Figure G.1 – 2-parameter TRV envelope representation of 1-cosineTRV when interrupting three-phase symmetrical fault currents Table G.2 – A comparison between the TRV terminology and symbols usedin IEC 62271-100 with those used in older IEEE/ANSI standards |
218 | Annex H (informative)Determination of the degree of asymmetry forgenerator-source short-circuit breaking tests |
219 | Figure H.1 – Prospective generator-source short-circuit current(fault initiation at voltage zero) |
220 | Annex I (informative)Faults in case of three-winding step-up transformer Figure I.1 – Single-line diagram of a power station with two generators connected to the high-voltage system by means of a three-winding step-up transformer |
221 | Figure I.2 – Prospective system-source short-circuit current to be interrupted by Generator circuit-breaker #1 in case of three-phase earthed fault occurring at location F in Figure I.1 (only the current in the phase with the highest degree of asymmetry is shown – fault initiation at voltage = 0) Table I.1 – A comparison between prospective system-source short-circuit currentsto be interrupted by Generator circuit-breaker 1 in case of three-phase earthedfault occurring at location F in Figure I.1 |
222 | Figure I.3 – Prospective fault current fed by Generator 2 to be interrupted by Generator circuit-breaker 2 in case of three-phase earthed fault occurring at location F in Figure I.1 (only the current in the phase with the highest degree of asymmetry is shown – fault initiation at voltage = 0) |
223 | Bibliography |